MENU
For a better view on Kailani Grand Cayman Curio Collection Hilton, Update Your Browser.

Feature Collection

  • 1. Seventh floor spa spanning the entire top storey of the hotel featuring a state-of-the-art gym, yoga studio, thermal spa, sauna, hydro pool and more.
  • 2. Two farm-to-table restaurants
  • 3. Resort-style pool with swim-up bar
  • 4. Juice bar
  • 4. In-room wellness amenities
  • 5. Concierge
  • 9. Electric vehicle rentals
  • 10. Bicycles for guest use
  • 11. Wellness excursions
  • 12. Onsite watersports
  • 13. Conference and meeting facilities
  • 14. Parking
  • 15. Free high speed internet and wifi

Construction Update

Construction Update

December 2021

Construction on the Kailani site continues to move along at a steady pace. The Phase 2 structure has progressed to the 7th floor level and the team is continuing works on the Phase 3 basement. The fit out of the hotel’s model room is currently in process and ongoing.

PHASE 1
  • This structure has been completed. The windows are currently on site and awaiting installation for further approval. The hardware for the windows has recently arrived.
  • The arrival of the window/door installers is expected early 2022
  • Construction of Phase 1’s concrete slab canopy over the entry doors has been complete
PHASE 2
  • Concrete pour of the 7th floor roof slab is scheduled for pour during the first weeks of 2022
  • The 3rd floor walls have been completed
  • The staircase’s fire protection, electrical and plumbing works are roughed in up to the 7th floor level
  • The model room’s stud framing is completed, and the unit is waterproofed
  • Plumbing, electrical, mechanical and dry/wet fire protection rough-ins are all completed
  • Both walls were boarded, and MEP inspections were approved for drywall installation on general walls and ceiling
  • Staircase is completed up to the 7th floor roof level
  • Metal framing has been completed in Units 202, 203, 204 and 205 (2nd floor)
PHASE 3
  • Plumbing was completed in the NW corner of the basement and inspection was approved
  • Electrical main conduits were installed in the NW corner of the basement
  • Floor drains and catch basins are in place and plumbing completed in the NW corner
  • A portion of the basement slab has been poured on the south side
  • Recently poured concrete for strip footings in the NW corner of the basement and laced up the walls with rebar
  • Poured concrete for the F8 bases along the NW corner